Sepasoft MES - How to show Process Segments(Maintenance, Changeover, Production) in Schedule View?

Right now I am trying to do this in Vision but I actually wanted to configure and show process segments in Schedule view in Perspective. But in perspective MES object editor component is not available. So I am able to add work orders in Schedule view but How to add Process segments here?

Manual link,
MES Schedule View (sepasoft.com)

I want to show the schedule view like thiis,

Unfortunately, Sepasoft has lacked greatly in terms of their perspective components versus their vision ones.

@jesse.records Is a great guy to help with stuff like this.

Although we have ~60 components published in Perspective, there is currently no plan to develop the Object Editor in Perspective.

I think it would be good to get on a call to discuss your objectives in more detail.

Sure. But I am not available today so will see later. Thank you