Vision 8.1.32
I believe the plant inadvertently exported some resources that overwrote like named windows/ templates across projects. I was able to restore some specific windows from an older backup I had while the plant contacted IT to get a restore of the server backup. In that time, another integrator made some project and gateway changes that I don't want to lose.
So, I restored the server backup onto a VM, did a gateway restore, and exported the projects that were affected.
My plan is to import those today.
What is the best method. What happens to the actively running clients during the restore.
My plan was to rename each affected project incase the new imports go haywire, import the backed up projects, and then once everything looks correct, delete the backups.
I guess my question is what happens to the clients when I rename the project in the gateway before importing the backups? Should I stop the gateway before doing this and terminate all clients?